ASSEMBLY OF THE FINAL AUDIT FILE


 Assembly of the Final Audit File

The auditor shall assemble the audit documentation in an audit file and complete the administrative process of assembling the final audit file on a timely basis after the date of the auditor’s report.

SQC 1 “Quality Control for Firms that perform Audits and Review of Historical Financial Information, and other Assurance and related services”, requires firms to establish policies and procedures for the timely completion of the assembly of audit files. An appropriate time limit within which to complete the assembly of the final audit file is ordinarily not more than 60 days after the date of the auditor’s report.

The completion of the assembly of the final audit file after the date of the auditor’s report is an administrative process that does not involve the performance of new audit procedures or the drawing of new conclusions. Changes may, however, be made to the audit documentation during the final assembly process, if they are administrative in nature.

After the assembly of the final audit file has been completed, the auditor shall not delete or discard audit documentation of any nature before the end of its retention period.

SQC 1 requires firms to establish policies and procedures for the retention of engagement documentation. The retention period for audit engagements ordinarily is no shorter than seven years from the date of the auditor’s report, or, if later, the date of the group auditor’s report.