Effects of Failure to Perform at a Time Fixed in a Contract in which Time is Essential(Section 55)
The law on the subject is contained in Section 55 which is reproduced below:
“When a party to a contract promises to do certain thing at or before the specified time, and fails to do any such thing at or before the specified time, the contract, or so much of it as has not been performed, becomes voidable at the option of the promisee, if the intention of the parties was that time should be of essence of the contract”.
Euect of such failure when time is not essential
If it was not the intention of the parties that time should be of essence of the contract, the contract does not become voidable by the failure to do such thing at or before the specified time; but the promisee is entitled to compensation from the promisor for any loss occasioned to him by such failure.
Effect of acceptance of performance at time other than agreed upon -
If, in case of a contract voidable on account of the promisor’s failure to perform his promise at the time agreed, the promisee accepts performance of such promise at any time other than agreed, the promisee cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless, at the time of acceptance, he gives notice to the promisor of his intention to do so.
Analysis of Section 55
But ordinarily, from an examination of a contract, it is diflcult to ascertain whether time is intended to be of essence by the parties at the time of its formation. In every case, the intention is to be gathered from the terms of the contract.
In a mercantile contract, the general rule in this regard is that stipulations as to time, except as to time for payment of money, are essential conditions, since punctuality is of the utmost importance in the business world. Thus, on a sale of goods that are notoriously subject to rapid fluctuation of market price, e.g. gold, silver, shares having a ready market the time of delivery is of the essence of the contract. But in mortgage bond, the time fixed for the repayment of the mortgage money can by no means be regarded as an essential condition; consequently, the mortgaged property can be regained even after the due date. Similarly, in a contract to sell land any clause limiting the time of completion is not strictly enforced. But even in a contract for the sale of land, time can be made the essence of the contract by express words.
Contract cannot be avoided where time is not essential: Where time is not essential, the contract cannot be avoided on the ground that the time for performance has expired, there the promisee is only entitled to compensation from the promisor for any loss caused by the delay. But it must be remembered that even where time is not essential it must be performed within a reasonable time; otherwise it becomes voidable at the option of the promisee.
Effect of acceptance of performance out of time:
Even where time is essential the promisee may waive his right to repudiate the contract, when the promisor fails to perform the promise within the stipulated time. In that case, he may accept performance at any time other than that agreed. In such an event, he cannot claim compensation for any loss occasioned by the non-performance of the promise at the time agreed, unless at the time of acceptance of the performance he has given a notice to the promisor of his intention to claim compensation.
No comments:
Post a Comment