Distinction between liquidated damages and penalty
Penalty and liquidated damages have one thing in common that both are payable on the occurrence of a breach of contract. It is very diflcult to draw a clear line of distinction between the two but certain principles as laid down below may be helpful.
1. If the sum payable is so large as to be far in excess of the probable damage on breach, it is certainly a penalty.
2. Where a sum is expressed to be payable on a certain date and a further sum in the event of default being made, the latter sum is a penalty because mere delay in payment is unlikely to cause damage.
3. The expression used by the parties is not final. The court must find out whether the sum fixed in the contract is in truth a penalty or liquidated damages. If the sum fixed is extravagant or exhorbitant, the court will regard it is as a penalty even if, it is termed as liquidated damages in the contract.
4. The essence of a penalty is payment of money stipulated as a terrorem of the ouending party. The essence of liquidated damages is a genuine pre-estimate of the damage.
5. English law makes a distinction between liquidated damages and penalty, but no such distinction is followed in India. The courts in India must ascertain the actual loss and award the same which amount must not, however exceed the sum so fixed in the contract. The courts have not to bother about the distinction but to award reasonable compensation not exceeding the sum so fixed.